List of questions
Related questions
Question 47 - PMI-RMP discussion
The risk manager conducted an updated Monte Carlo simul-ation for the project at the end of a phase. The simul-ation reveals a key activity is now on the critical path.
What recommendation should the risk manager make to the project manager?
A.
Add more float to the key activity
B.
Add more contingency to the project
C.
Review the plans for the key activity
D.
Increase the budget for the key activity
Your answer:
0 comments
Sorted by
Leave a comment first