A budget change request was initiated by a functional manager in an organization due to a shortage in the functional manager's department budget. The functional manager asks the CEO to approve utilization of a contingency budget reserved for one of the projects in its closing phase.

What should the risk manager of the related project have done to prevent this situation from happening?

A.

Reformed the risk monitoring and closing process properly.

Answers
A.

Reformed the risk monitoring and closing process properly.

B.

Created the project work plan and budget more accurately.

Answers
B.

Created the project work plan and budget more accurately.

C.

Educated the project team on budget change requests.

Answers
C.

Educated the project team on budget change requests.

D.

Communicated better with the organization's CEO.

Answers
D.

Communicated better with the organization's CEO.

Suggested answer: A

Explanation:

According to the PMI Risk Management Professional (PMI-RMP) Handbook1, one of the domains of the PMI-RMP exam isRisk Monitoring and Reporting, which involves tracking identified risks, monitoring residual risks, identifying new risks, executing risk response plans, and evaluating risk process effectiveness throughout the project1. The risk manager of the related project should have reformed the risk monitoring and closing process properly to ensure that the contingency budget is only used for the intended risks and not for other purposes.The risk manager should have also communicated the status and outcomes of the risk activities to the relevant stakeholders, such as the functional manager and the CEO, to avoid any confusion or conflict over the budget allocation1.Reference:1: PMI Risk Management Professional (PMI-RMP) Handbook, page 6.

The risk manager should have ensured a more accurate project work plan and budget to prevent the functional manager from requesting to use the project's contingency budget. A well-planned budget would have avoided the shortage in the functional manager's department budget.