Question 53 - PMI-RMP discussion
The project risk manager is in the process of identifying risks. The project sponsor has communicated that there is an influential stakeholder who has a senior management position. The other stakeholders do not feel comfortable speaking in front of this stakeholder.
What should the project risk manager do next to identify risks?
A.
Review the risk breakdown structure to ensure project scope is covered.
B.
Use the brainstorming technique to remove personal bias.
C.
Use expert judgment to remove ego or emotional conflict.
D.
Consider the Delphi technique to gather all stakeholder opinions.
Your answer: