Question 54 - PMI-RMP discussion
A certain risk is identified for a major project, and the risk response is planned. However, the analysis reveals a high probability for a secondary risk which will be tolerated based on the organization's risk thresholds. The secondary risk is subsequently registered. During project execution, the primary risk occurs, the planned action is taken, and the secondary risk emerges
What two actions should the risk owner take? (Choose two.)
Implement the secondary risk response and update the project documents.
Conduct meeting with all stakeholder to agree on post impact solutions.
Set the corresponding trigger conditions to the secondary risk.
Engage the project manager to authorize the secondary risk's response.
Update and communicate assessments of the secondary risk's impact.