A project manager identified a risk of communication issues with the client which may impact the project schedule. A member of (he sales team advises that this client prefers face-to- face conversations.
What should the project manager do to avoid this risk?
A.
Record this risk and the clients preference in the risk register.
B.
Ask the sales person to lead the communication with the client
C.
Call the client and advise that online communication is easier and faster.
D.
Meet the client and plan tor critical milestone meetings.