ExamGecko
Question list
Search
Search

List of questions

Search

Related questions











Question 71 - PMI-RMP discussion

Report
Export

A complex project that had hundreds of risks is almost done. The project manager is closing the risks as part of the closing process. One team member mentions that there are important documents to be updated.

Which document will need to be updated?

A.

Lessons learned

Answers
A.

Lessons learned

B.

Contingency register

Answers
B.

Contingency register

C.

Risk register

Answers
C.

Risk register

D.

Issue log

Answers
D.

Issue log

Suggested answer: A

Explanation:

When closing risks as part of the closing process, it is important to update the lessons learned document. This document captures the knowledge and experience gained during the project and can be valuable for future projects.

Lessons learned is a document that captures the knowledge gained from the project and can help improve the performance of future projects. It is one of the outputs of the project closure process and should include information on the project risks, issues, and responses. Lessons learned can help identify the best practices and lessons to be applied or avoided in similar projects. Updating the lessons learned document is an important part of closing the risks as it can provide valuable insights for risk management.Reference:PMI, Project Risk Management, 2nd edition, 2019, p.97-981

asked 14/11/2024
Melvin Bruijnaers
33 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first