After a number of risk workshops, risks have been identified. Which is the first element the risk owner should look for in the response plan to help mitigate the risks?
A.
Probability of a response triggering a secondary risk
B.
How the response will affect the quality of the components
C.
If the risk response is tied to an activity on the critical path
D.
Verify due dates for the actions have been identified