Question 81 - PMI-RMP discussion
The project risk manager for an environmental preservation project has started the process of monitoring and controlling risks, The project manager has asked the project team to document the results of this process.
How should this documentation be utilized in the future?
A.
To return the remaining amount of the contingency reserve
B.
To ensure information is recorded for lessons learned
C.
To comply with the rules and regulations
D.
To hold those who created the risk accountable