List of questions
Related questions
Question 90 - PMI-RMP discussion
The project team has correctly identified, assessed, and planned responses for a project's risks. The risk manager is required to prepare a quarterly report on the performance of managing the risks.
What are two options the risk manager should consult for the analysis? (Choose two.)
A.
Proximity dales for open risks
B.
Backlog of change orders to be submitted to client
C.
Risks that have materialized and the overall risk profile
D.
Number of schedule baseline changes approved
E.
Risks due to the number of claims submitted to the client
Your answer:
0 comments
Sorted by
Leave a comment first