ExamGecko
Question list
Search
Search

List of questions

Search

Related questions











Question 96 - PMI-RMP discussion

Report
Export

During the weekly project meeting a risk manager identified new risks in the last sprint, which might impact the project cost by implementing mitigation plans. The sponsor and some project team members do not agree that those risks can impact the project cost.

What should the risk manager do to resolve the sponsor and project team members' concerns about risk identification?

A.

Reinforce to the stakeholders that the risk identification was done properly during the last sprint.

Answers
A.

Reinforce to the stakeholders that the risk identification was done properly during the last sprint.

B.

Highlight the importance of agreeing on the risk identification to avoid further delays.

Answers
B.

Highlight the importance of agreeing on the risk identification to avoid further delays.

C.

Conduct a separate meeting to show the risk identification analysis to the stakeholders.

Answers
C.

Conduct a separate meeting to show the risk identification analysis to the stakeholders.

D.

Ensure that the most knowledgeable members of the team validate risk identification processes.

Answers
D.

Ensure that the most knowledgeable members of the team validate risk identification processes.

Suggested answer: C
asked 14/11/2024
Ben Pike
33 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first