Question 114 - PMI-RMP discussion
When approving the risk contingency budget for a project, the CEO notices each team has a different approach to report risks and their impacts. The CEO decides to create a new centralized risk management function to help resolve the problem.
How does centralizing the risk management function help resolve the problem?
A.
Enhance the process of identification of different Individual project risks.
B.
Allows monitoring the impact against the overall project risk exposure.
C.
Establishes risk sources and ownership for trigger monitoring.
D.
Creates a single repository for all project risk documents.