List of questions
Related questions
Question 119 - PMI-RMP discussion
A risk manager and relevant stakeholders have completed a risk response plan for a project. They have identified and planned responses to the known risks; however, a risk owner has identified and reported some residual risks not previously addressed.
What should the risk manager do first?
A.
Develop a residual risk management plan to manage the residual risks.
B.
Analyze, document, and communicate the residual risks to stakeholders.
C.
Record the residual risks in the watch list for future reference.
D.
Implement the contingency plan when the residual risks occur.
Your answer:
0 comments
Sorted by
Leave a comment first