Question 121 - PMI-RMP discussion
A project manager realizes the team undertaking the project work has fallen behind the planned schedule. The risk manager identifies a new risk resulting from this delay and will need to understand how this will affect the project deadline.
Which kind of numerical analysis should be performed to understand the worst-case scenarios?
A.
Earned value analysis
B.
Qualitative risk analysis
C.
Sensitivity analysis
D.
Root cause analysis