During a risk identification process in a construction project, the lack of space to install air conditioners is raised as a risk with high impact. Which is an example of an early risk trigger?
A.
A potential need to share the space with other machinery
B.
A different type of equipment received before installation
C.
A time delay during air conditioning installation activities
D.
A quality nonconformance issue raised during the inspection