Question 129 - PMI-RMP discussion
An external vendor needs to be contracted to provide additional capacity and expertise to a project team to reduce the probability of delays in a project. The contracts department is raising a concern about confidentiality risks not addressed in the proposed contract and missing from the risk register.
What should the risk manager do next?
A.
Assess the identified secondary risk.
B.
Implement the risk response plan.
C.
Implement the risk contingency plan.
D.
Communicate the identified residual risk.
Your answer: