Question 151 - PMI-RMP discussion
A risk manager has identified multiple risks in an innovation project and needs to prioritize the use of resources to respond to the risks. Which analysis will help the risk manager in this situation?
A.
Sensitivity analysis
B.
Qualitative analysis
C.
Statistical analysis
D.
Impact analysis