A risk manager has identified multiple risks in an innovation project and needs to prioritize the use of resources to respond to the risks. Which analysis will help the risk manager in this situation?

A.

Sensitivity analysis

Answers
A.

Sensitivity analysis

B.

Qualitative analysis

Answers
B.

Qualitative analysis

C.

Statistical analysis

Answers
C.

Statistical analysis

D.

Impact analysis

Answers
D.

Impact analysis

Suggested answer: B