During the risk management planning, key stakeholders recommend adding more factors other than probability and the impact to refine the score of prioritized threats in subsequent iterations of the qualitative risk analysis. The stakeholders ask the risk manager to prepare a list to discuss this further.

Which three valid factors should the risk manager prepare on the list for discussion? (Choose 3)

A.

Compatibility

Answers
A.

Compatibility

B.

Urgency

Answers
B.

Urgency

C.

Usability

Answers
C.

Usability

D.

Proximity

Answers
D.

Proximity

E.

Detectability

Answers
E.

Detectability

Suggested answer: B, D, E