A risk manager has a well-structured risk management process in place for a complex project with a tight schedule. Despite implementing preventive actions, one of the risks identified in the early stages of the project has still occurred and is now an issue.
What should the risk manager do next?
A.
Meet with the project team to brainstorm potential solutions to the problem.
B.
Implement the risk response plan to remedy the problem as soon as possible.
C.
Initiate discussions with the project manager to decide how to manage the problem.
D.
Escalate the problem to the project sponsor to agree on the best course of action.