Question 155 - PMI-RMP discussion
A project team has completed the risk identification steps in a project and compiled a list of 25 risks. The team wants to create response plans for all the risks to avoid any future issues, but the resources and constraints limit the options.
What should the risk manager do?
A.
Perform a sensitivity analysis.
B.
Perform a qualitative risk analysis.
C.
Perform a constraint analysis.
D.
Perform a root-cause analysis.