A project team has completed the risk identification steps in a project and compiled a list of 25 risks. The team wants to create response plans for all the risks to avoid any future issues, but the resources and constraints limit the options.

What should the risk manager do?

A.

Perform a sensitivity analysis.

Answers
A.

Perform a sensitivity analysis.

B.

Perform a qualitative risk analysis.

Answers
B.

Perform a qualitative risk analysis.

C.

Perform a constraint analysis.

Answers
C.

Perform a constraint analysis.

D.

Perform a root-cause analysis.

Answers
D.

Perform a root-cause analysis.

Suggested answer: B