A project team working on a large software deployment project for a few months has been able to prevent a technical risk from occurring. However, an incident took place and triggered the technical issue.

What should the risk manager do?

A.

Execute the risk response plan defined for the risk.

Answers
A.

Execute the risk response plan defined for the risk.

B.

Postpone the software launch to sort out the technical issue.

Answers
B.

Postpone the software launch to sort out the technical issue.

C.

Meet with the project manager to revisit the project schedule.

Answers
C.

Meet with the project manager to revisit the project schedule.

D.

Assess the impacts and define the response actions with the subject matter experts (SMEs).

Answers
D.

Assess the impacts and define the response actions with the subject matter experts (SMEs).

Suggested answer: A