Question 158 - PMI-RMP discussion
A risk manager wants to determine what risk has the biggest impact on project cost. The risk manager identified three risks, which could occur in different phases of the project.
What should the risk manager do first to understand the impact on project cost?
A.
Prioritize after quantitative analysis.
B.
Perform qualitative analysis.
C.
Prioritize the stakeholders affected.
D.
Conduct a subject matter expert (SME) meeting.
Your answer: