During a project meeting, the project sponsor asks to close a project risk. The team does not recommend closing the risk because it is expected to be present in the next phase of the project work.

How should the risk manager address this concern?

A.

Compare the actual data with the subject matter expert (SME) criteria.

Answers
A.

Compare the actual data with the subject matter expert (SME) criteria.

B.

Compare the actual data with the historical data.

Answers
B.

Compare the actual data with the historical data.

C.

Compare the actual data with the risk baseline.

Answers
C.

Compare the actual data with the risk baseline.

D.

Compare the actual data with the project sponsor's expectation.

Answers
D.

Compare the actual data with the project sponsor's expectation.

Suggested answer: C