The risk manager loaded the risk register, built the risks into the simulation software, and ran the Monte Carlo analysis The P80 and P90 end dates are the same as the deterministic date.

What should be the risk manager's next step?

A.

Check the schedule for constraints

Answers
A.

Check the schedule for constraints

B.

Decrease the risk consequences

Answers
B.

Decrease the risk consequences

C.

Decrease the number of iterations

Answers
C.

Decrease the number of iterations

D.

Use the P90 date on the risk report

Answers
D.

Use the P90 date on the risk report

Suggested answer: A