After the initial assessment of a new project, a project manager found that in order to complete the expected results, detailed and exhaustive planning will be required to ensure the product's characteristics and quality. What should the risk manager propose to the project manager what to do?
A.
Use a predictive approach for the delivery.
B.
Use a hybrid approach for the delivery.
C.
Use an adaptive approach for the delivery.
D.
Use an agile approach for the delivery.