In a large enablement project with strict time lines, risks need to be closely monitored. The risk manager publishes reports comparing planned enablement sessions with actual enablement sessions, which help identify potential risks to be addressed.

Which technique is the risk manager using?

A.

Variance analysis

Answers
A.

Variance analysis

B.

Residual impact analysis

Answers
B.

Residual impact analysis

C.

Sensitivity analysis

Answers
C.

Sensitivity analysis

D.

Reserve analysis

Answers
D.

Reserve analysis

Suggested answer: A