Question 173 - PMI-RMP discussion
A complex infrastructure construction project consisting of various stakeholders with diverse attitudes and opinions is in the execution phase. The project sponsor instructed the risk manager to evaluate the project environment and identify potential risks because many conflicts have arisen.
What should the risk manager do first?
A.
Perform an assumptions and constraints analysis.
B.
Use the Wideband Delphi method.
C.
Use the brainstorming technique.
D.
Perform a strength, weaknesses, opportunities, and threats (SWOT) analysis.