A project team is presenting a delivery plan to a client. Some of the client's experts do not feel comfortable with some activities at a critical stage. The experts ask to change the plan and present a better alternative.

What should the risk manager do first?

A.

Review and update the project quality management plan.

Answers
A.

Review and update the project quality management plan.

B.

Conduct a risk assessment process for the critical stage.

Answers
B.

Conduct a risk assessment process for the critical stage.

C.

Create a more detailed work breakdown structure (WBS).

Answers
C.

Create a more detailed work breakdown structure (WBS).

D.

Add additional time to the delivery plan to cover issues.

Answers
D.

Add additional time to the delivery plan to cover issues.

Suggested answer: B