Question 175 - PMI-RMP discussion
The stakeholders of a building construction project are not comfortable with the project manager's handling of the project as they believe there is a financial risk. The project manager asks the risk manager to assist in demonstrating to the stakeholders that the project risks are under a tolerable threshold.
What should the risk manager do first to demonstrate this to the stakeholders?
A.
Gather other project risk historical information.
B.
Gather and reconcile project risk report data.
C.
Work with the sponsor to convince the risks are under control.
D.
Work with the team to ensure the project is in good health.