Question 183 - PMI-RMP discussion
A critical piece of equipment broke during a project execution phase. The risk manager notices this risk in the risk register, and the response is to rent equipment until the critical piece is repaired.
What type of risk response is this?
A.
Transfer
B.
Accept
C.
Mitigate
D.
Avoid
Your answer: