A key project is delayed and all contingency reserves have been used even though the project team has implemented all planned risk responses. What should the risk manager do next?

A.

Create a new project plan including the new risks.

Answers
A.

Create a new project plan including the new risks.

B.

Review the effectiveness of the risk process.

Answers
B.

Review the effectiveness of the risk process.

C.

Update the risk management plan.

Answers
C.

Update the risk management plan.

D.

Escalate the project risks to upper management.

Answers
D.

Escalate the project risks to upper management.

Suggested answer: D