Question 193 - PMI-RMP discussion
A risk manager monitors risks on a medium-sized project by collecting inputs and data from individual project team members. What output is produced by the risk manager after analyzing the information they receive?
A.
Updated probability and impact matrix
B.
Updated risk register
C.
Updated mitigation plans
D.
Updated project schedule