A risk manager monitors risks on a medium-sized project by collecting inputs and data from individual project team members. What output is produced by the risk manager after analyzing the information they receive?

A.

Updated probability and impact matrix

Answers
A.

Updated probability and impact matrix

B.

Updated risk register

Answers
B.

Updated risk register

C.

Updated mitigation plans

Answers
C.

Updated mitigation plans

D.

Updated project schedule

Answers
D.

Updated project schedule

Suggested answer: B