A risk manager has been assigned to replace a risk manager on sick leave. The new risk manager notices that the risk register is missing data that are key to the risk management process.

Which data will the risk manager require first?

A.

Risk description risk response, and quantitative data

Answers
A.

Risk description risk response, and quantitative data

B.

Project plan, risk complexity, and secondary risk

Answers
B.

Project plan, risk complexity, and secondary risk

C.

Project plan, risk priority, and tool availability

Answers
C.

Project plan, risk priority, and tool availability

D.

Risk description, risk probability, and risk impact

Answers
D.

Risk description, risk probability, and risk impact

Suggested answer: C