Question 574 - CGEIT discussion
In a large enterprise, which of the following is the BEST approach to enable effective communication to senior management regarding the project status for a strategic enterprise resource management system implementation?
A.
Project management office with business and IT representatives
B.
Weekly project reports reviewed by business and IT management
C.
Project status updates on the intranet
D.
A steering committee involving business and IT