What is the purpose of the scrum board?

A.

To show readiness of the release

Answers
A.

To show readiness of the release

B.

To visualize the resource load

Answers
B.

To visualize the resource load

C.

To visualize team progress

Answers
C.

To visualize team progress

D.

To document the results of the fit-to-standard workshop

Answers
D.

To document the results of the fit-to-standard workshop

Suggested answer: C

Explanation:

The scrum board is used to visually track team progress on sprint tasks. By displaying each task's current status, it provides transparency, helping team members and stakeholders stay updated on the sprint's progress.