Development team A is consistently overestimating the work they can complete per sprint. They want to be able to compare work committed and work completed in sprints over time. Which single report provides this information?

A.
Control Chart
Answers
A.
Control Chart
B.
Sprint Report
Answers
B.
Sprint Report
C.
Cumulative Flow Diagram
Answers
C.
Cumulative Flow Diagram
D.
Created vs Resolved Issues Report
Answers
D.
Created vs Resolved Issues Report
E.
Velocity Chart
Answers
E.
Velocity Chart
Suggested answer: E

Explanation:

The Velocity Chart is the best report to compare work committed and work completed in sprints over time. It shows the average amount of work that a team can complete in a sprint, based on the historical data of previous sprints. It also shows how much work was planned and how much was actually completed in each sprint. By looking at the Velocity Chart, a team can see if they are overestimating or underestimating their capacity, and adjust their planning accordingly. Therefore, option E is correct.Reference:Velocity Chart,Managing Jira Projects Data Center and Server: Certification Bundle