Your program has 121 stakeholders that you'll need to communicate with. Your communications management plan defines how the communication should happen, what should be communicated, and the expected modality of the communications. You'll also need which one of the following as an input to the information distribution process in your program?

A.
Change requests
Answers
A.
Change requests
B.
Earned value management results
Answers
B.
Earned value management results
C.
Stakeholder analysis plan
Answers
C.
Stakeholder analysis plan
D.
Performance reports
Answers
D.
Performance reports
Suggested answer: C