List of questions
Related questions
Question 447 - PgMP discussion
To create market advantage, a program sponsor requests accelerating the implementation of a new manufacturing process that is based on a recently improved system component. The program manager is concerned that the delivery of some program goals could be jeopardized.
What should the program manager do?
A.
Document the concerns that program goals may be affected and present at the next program governance board review meeting for guidance and actions to be taken
B.
Advise the program sponsor that the program will continue and follow the program management plan, unless the change control board (CCB) has approved changes to the plan
C.
Work with the project managers of the affected components to implement fast tracking and update the resource management plan accordingly
D.
Evaluate critical success factors and key performance indicators (KPIs) to monitor benefits throughout the program's life cycle
Your answer:
0 comments
Sorted by
Leave a comment first