Question 446 - PgMP discussion
The project managers for component projects A and B schedule the same resource to perform tasks during the same timeframe, resulting in an over-allocation.
The program manager reviews the program resource management plan, determines that project A can wait until the resource becomes available, and assigns the resource to project B.
This is an example of which of the following?
A.
Program resource management planning
B.
Program risk mitigation
C.
Resource interdependency management
D.
Project resource planning