Question 3 - PgMP discussion
Olive is the program manager for her organization. She has created a request for proposal for a large portion of her program. In this work to be procured she has set several requirements for the vendors to participate. The chief among these requirements is a vendor must have at least four licensed electricians in his team.
This requirement for four licensed electricians is an example of which one of the following terms?
A.
Screening system
B.
Scoring model
C.
Vendor analysis requirements
D.
Evaluation criteria
Your answer: