Your program has 121 stakeholders that you'll need to communicate with. Your communications management plan defines how the communication should happen, what should be communicated, and the expected modality of the communications. You'll also need which one of the following as an input to the information distribution process in your program?

A.
Change requests
A.
Change requests
Answers
B.
Earned value management results
B.
Earned value management results
Answers
C.
Stakeholder analysis plan
C.
Stakeholder analysis plan
Answers
D.
Performance reports
D.
Performance reports
Answers
Suggested answer: C

What is the formula to determine earned value (EV) for a program?

A.
Percent complete times percent remaining in the program
A.
Percent complete times percent remaining in the program
Answers
B.
Percent completes time the program cost estimate
B.
Percent completes time the program cost estimate
Answers
C.
Percent complete times the program budget at completion
C.
Percent complete times the program budget at completion
Answers
D.
Percent complete times the program cost of labor and materials
D.
Percent complete times the program cost of labor and materials
Answers
Suggested answer: C

Olive is the program manager for her organization. She has created a request for proposal for a large portion of her program. In this work to be procured she has set several requirements for the vendors to participate. The chief among these requirements is a vendor must have at least four licensed electricians in his team.

This requirement for four licensed electricians is an example of which one of the following terms?

A.
Screening system
A.
Screening system
Answers
B.
Scoring model
B.
Scoring model
Answers
C.
Vendor analysis requirements
C.
Vendor analysis requirements
Answers
D.
Evaluation criteria
D.
Evaluation criteria
Answers
Suggested answer: A

You are the program manager for your organization. Management has asked you to create a document that will capture the stakeholders concerns, perceived threats, and specific objectives about the program and its projects. What document is management asking you to create in this instance?

A.
Requirements document
A.
Requirements document
Answers
B.
Project charter
B.
Project charter
Answers
C.
Business case
C.
Business case
Answers
D.
Scope statement
D.
Scope statement
Answers
Suggested answer: D

You are the program manager of the NHQ Program. You are working with your program team to ensure that the work in the program is done accurately and according to scope. You are also reviewing the team inspection process that will need to be done to ensure that the work is being done according to the scope. If the work is found to be defective it will need to be corrected before the program customers can inspect the work. What process are you completing to ensure that the work is done accordingly to scope?

A.
Quality control
A.
Quality control
Answers
B.
Scope verification
B.
Scope verification
Answers
C.
Quality assurance
C.
Quality assurance
Answers
D.
Planning
D.
Planning
Answers
Suggested answer: C

Your company and a competing company have created a teaming agreement for an opportunity. Through this team agreement you and your competitor can complete a major program for a client. This is, technically, a risk response for both organizations. What type of risk response are you dealing with in this instance?

A.
Teaming
A.
Teaming
Answers
B.
Exploiting
B.
Exploiting
Answers
C.
Accepting
C.
Accepting
Answers
D.
Sharing
D.
Sharing
Answers
Suggested answer: D

A project manager in your program has estimated the cost of a program to be $145,000. As the project manager's project comes close to completion, the project manager realizes that he has still $27,876 left in his project budget. He decides to add some additional features to the project's deliverables in an effort to use the remaining budget. These additions will add value to the project and the project customer is likely to enjoy these new features. This is an example of what term?

A.
Gold plating
A.
Gold plating
Answers
B.
Errors and omissions
B.
Errors and omissions
Answers
C.
Expert judgment by the project manager
C.
Expert judgment by the project manager
Answers
D.
Value added change
D.
Value added change
Answers
Suggested answer: A

Andy is the program manager of the HQN Program. This program is nearing its completion and there is still $25,000 left in the program budget. Andy has asked the program team to identify some extra deliverables that can be included in the program scope to improve the program deliverable but also to use all of the funds in the budget. What term is assigned to the actions that Andy is trying to do in this instance?

A.
Value-added change requests
A.
Value-added change requests
Answers
B.
Zero based budgeting
B.
Zero based budgeting
Answers
C.
Integrated change control
C.
Integrated change control
Answers
D.
Gold plating
D.
Gold plating
Answers
Suggested answer: D

What analysis type could you use in a program to compare the positive stakeholders and their position, power, and influence over your program to the same variable components of the negative stakeholders in your program?

A.
Sensitivity analysis
A.
Sensitivity analysis
Answers
B.
Stakeholder analysis
B.
Stakeholder analysis
Answers
C.
Monte Carlo simulation
C.
Monte Carlo simulation
Answers
D.
Force field analysis
D.
Force field analysis
Answers
Suggested answer: D

You are the program manager of the BHG Program. One of the projects in your program will be using new materials that are somewhat untested. You are worried that there may be delays and waste because the project team is unaware of how to accurately use these materials. You elect to send the people that will be using the new materials through training on how to complete their project work. You also allow them to purchase some of the materials to experiment on their use before the actual project work is to be done. You want to ensure that mistakes do not enter into the project. What type of action have you provided in this scenario?

A.
This is an example of a preventive action.
A.
This is an example of a preventive action.
Answers
B.
This is an example of team development.
B.
This is an example of team development.
Answers
C.
This is an example of quality assurance.
C.
This is an example of quality assurance.
Answers
D.
This is an example of a corrective action.
D.
This is an example of a corrective action.
Answers
Suggested answer: A