ExamGecko
Home / PMI / PgMP / List of questions
Ask Question

PMI PgMP Practice Test - Questions Answers, Page 4

Add to Whishlist

List of questions

Question 31

Report Export Collapse

Terri is the program manager for her organization and she's working with Alice, a project manager in her program. Alice calls Terri and insists that she add a change to program scope. Terri agrees that the change should be entertained. What must Alice do to move forward with her change request?

Add the change to the program scope herself, as she is a project manager
Add the change to the program scope herself, as she is a project manager
Add the change request to the scope and complete integrated change control
Add the change request to the scope and complete integrated change control
Document the change request in a change request form.
Document the change request in a change request form.
Create a change request charter justifying the change request
Create a change request charter justifying the change request
Suggested answer: C
asked 23/09/2024
Juan Rodriguez
48 questions

Question 32

Report Export Collapse

You are the program manager for the NHQ Program. Your program has a budget of $4,500,000 and has lasted for two years. Your program has just completed its final deliverable and you're completing the final program closure processes. What document must the program customer must now sign as part of program closure?

The customer must now sign the program scope.
The customer must now sign the program scope.
The customer must now sign the payment for the program work.
The customer must now sign the payment for the program work.
The customer must now sign the certificate of program closure.
The customer must now sign the certificate of program closure.
The customer must now sign the operational transfer agreement.
The customer must now sign the operational transfer agreement.
Suggested answer: C
asked 23/09/2024
Alper Atar
48 questions

Question 33

Report Export Collapse

You are the program manager of the YGH Program. A vendor has recently completed his contracted work for your program. You agree that the vendor has completed the procured work so what document should you and the vendors now sign?

Certificate of completion
Certificate of completion
Proposal agreement
Proposal agreement
Invoice
Invoice
Contract
Contract
Suggested answer: A
asked 23/09/2024
Ilia Voronkov
46 questions

Question 34

Report Export Collapse

You are the program manager for your organization. Management has asked that you determine when resources, such as leased equipment, are no longer needed so that you may release the resources to save time, money, and utilization of resources within your program. What program management process is management asking you to perform?

Contract administration
Contract administration
Resource management
Resource management
Resource control
Resource control
Procurement management
Procurement management
Suggested answer: C
asked 23/09/2024
null null
49 questions

Question 35

Report Export Collapse

Molly is the program manager for her organization. She is creating a document that defines the benefits the program will create for her organization once the program has been completed. What document is Molly writing?

Program charter
Program charter
Program benefits realization plan
Program benefits realization plan
Program benefits statement
Program benefits statement
Program scope statement
Program scope statement
Suggested answer: C
asked 23/09/2024
safiqueahmed kazi
42 questions

Question 36

Report Export Collapse

You are the program manager for your organization. Management is considering a new program but they are worried about the program risks that may affect the program success. You know that there are three positive risks responses and three negative risk responses that each risk can have. Management asks you which risk response would be most appropriate for a large risk event if they wanted to hire a third-party to own the risk event for the program. What risk event is most appropriate?

Transference
Transference
Mitigation
Mitigation
Avoidance
Avoidance
Sharing
Sharing
Suggested answer: A
asked 23/09/2024
matthew kim
44 questions

Question 37

Report Export Collapse

You are the program manager for your organization. You have created a statement of work, request for proposal, and an invitation to a bidder's conference for 17 possible vendors. During the conference there were questions about your request for proposal and statement of work that led to clarifications. After the vendor conference you should update what information to send back to the vendors?

Request for bid documents
Request for bid documents
Proposals
Proposals
Statement of work
Statement of work
Program management plan
Program management plan
Suggested answer: C
asked 23/09/2024
Carlos Antonio Cardenas Lee
41 questions

Question 38

Report Export Collapse

You are the project manager for your organization and are working with the project stakeholders and the business analyst to define all of the deliverables the project is to create. The stakeholders would like the option of adding more deliverables later in the project and keeping the requirements somewhat open for changes. You explain to the business analyst that you need a set of requirements that define exactly what needs to be delivered for the project. What document are you trying to create in this early stage of the project?

Requirements technical documentation
Requirements technical documentation
Project scope statement
Project scope statement
Project charter
Project charter
Detail design document
Detail design document
Suggested answer: B
asked 23/09/2024
richard van der sligte
38 questions

Question 39

Report Export Collapse

A new program is being initiated for the HNQ Organization. The program manager is working with the business analyst and management to define several attributes of the program. All of the following are identified during program initiation except for which one?

Program risk
Program risk
Program benefits
Program benefits
Program scope
Program scope
Link to organizational strategy
Link to organizational strategy
Suggested answer: A
asked 23/09/2024
Jenny Maliwanag
55 questions

Question 40

Report Export Collapse

As a program manager you must also understand the project management lifecycle and the project lifecycle. What is the difference between the two?

The project management lifecycle and the project lifecycle are the same thing.
The project management lifecycle and the project lifecycle are the same thing.
The project management lifecycle is comprised of the phases initiating, planning, executing, monitoring and controlling, and closing. The project lifecycle is comprised of phases that are unique to the project work.
The project management lifecycle is comprised of the phases initiating, planning, executing, monitoring and controlling, and closing. The project lifecycle is comprised of phases that are unique to the project work.
The project management lifecycle is unique to each project while the project lifecycle is universal to all projects.
The project management lifecycle is unique to each project while the project lifecycle is universal to all projects.
The project management lifecycle is universal to all projects and the project lifecycle is unique to each project.
The project management lifecycle is universal to all projects and the project lifecycle is unique to each project.
Suggested answer: D
asked 23/09/2024
Neil Mallia
57 questions
Total 451 questions
Go to page: of 46
Search

Related questions