PMI PgMP Practice Test - Questions Answers, Page 29
List of questions
Related questions
The program sponsor requests a weekly performance report. The tools and techniques to monitor and control program performance include which of the following?
A new program is comprised of four component projects. The program manager must assign project managers to each of the four projects. There are eight potential project managers to consider.
What should the program manager do before assigning the project managers?
The chief executive officer reminds a program manager that a program must deliver a 30% reduction in customer complaints by the end of the year. Where is this expectation documented?
A two-year program is coming to an end. Many of the initial governance board members have moved from their current posts of left the company. Several new members have joined, but have a short association with the program, which changes the board's expectations and focus. During the final phase gate review, some board members are uncertain of their roles and expectations in the process.
How should the program manager handle this situation?
A program manager is working with the sponsor, stakeholders, and steering committee to formulate a program's benefits sustainment and transition plan. What should the program manager do to create this plan?
The program manager must define the program and understand the organization's target market and customer needs. What should the program manager do first?
A program manager notices that one project manager tends to withdraw during important team discussions to avoid conflict. What technique could the program manager use to gain more input from this project manager?
To increase its presence and promote its products and services in new markets, a company begins to implement its new business strategy. The company's CEO endorses a new program to promote and support this strategy. However, before the program is formally initiated, this strategy must be aligned with the organization's strategic goals and objectives.
What should the program manager develop first?
An organization requests that a junior project manager, with no previous experience or training in the industry, take over a complex program component. The program component involves senior subject matter experts and has dependencies with other large projects to deliver key benefits to the organization.
How should the junior project manager respond to this request?
Program A is dependent upon program B to complete benefits sustainment for two benefits. Program A is on track to meet program benefits. However, program
B's program manager has just advised that program B has been closed.
What should program A's program manager update and review first with the stakeholders?