PMI PgMP Practice Test - Questions Answers, Page 27

List of questions
Question 261

Which of the following can be used to help you or other project managers on future projects?
Question 262

What is the other name for critical delivery dates?
Question 263

Which of the following directs the improvement efforts to those areas that will have the biggest impact?
Question 264

Which of the following shows the ratio between a task's budgeted and actual costs?
Question 265

Which of the following increases when one fast tracks the project?
Question 266

Which of the following can be an effective tool during quality control to help determine the how the problem occurred?
Question 267

Which of the following terms is used for a schedule compression technique where two activities that were previously scheduled to start sequentially start at the same time?
Question 268

Which of the following individual should respond to the risk with the preplanned risk response?
Question 269

Which of the following information gathering techniques is described in the statement below?
"Project risk experts participate in this technique anonymously. A facilitator uses a Questionnaires to solicit ideas about the important project risks. The responses are summarized are then recirculated to the experts for further comment."
Question 270

Which of the following risk identification techniques is described in the statement below?
"It is used to gather information where participants don't know each other nor do they have to be present at the same location."
Question