You are the program manager for your organization. You are examining the order of the activities in your program schedule and would like to change some of the ordering to alleviate scheduling conflicts, risks, and based on your experience with the discipline the program uses. Some of the activities you can rearrange while some of the activities must be completed in a particular order. What term describes the activities that can happen in any order?

A.
Finish on constraints
A.
Finish on constraints
Answers
B.
Discretionary dependencies
B.
Discretionary dependencies
Answers
C.
Mandatory dependencies
C.
Mandatory dependencies
Answers
D.
Benefits management dependencies
D.
Benefits management dependencies
Answers
Suggested answer: C

You are the program manager for your organization and are planning the roles and responsibilities in your program. You would like to create a RACI chart for the program work. What does RACI mean?

A.
It is a roles and responsibilities chart that uses responsible, accountable, consult, and inform responsibilities as the chart legend.
A.
It is a roles and responsibilities chart that uses responsible, accountable, consult, and inform responsibilities as the chart legend.
Answers
B.
It is a roles and responsibilities chart that uses responsible, action, consult, and interest responsibilities as the chart legend.
B.
It is a roles and responsibilities chart that uses responsible, action, consult, and interest responsibilities as the chart legend.
Answers
C.
It is a roles and responsibilities chart that uses resource, action, contribute, inform responsibilities as the chart legend.
C.
It is a roles and responsibilities chart that uses resource, action, contribute, inform responsibilities as the chart legend.
Answers
D.
It is a roles and responsibilities chart that uses responsible, accountable, contribute, and inform responsibilities as the chart legend.
D.
It is a roles and responsibilities chart that uses responsible, accountable, contribute, and inform responsibilities as the chart legend.
Answers
Suggested answer: A

You are the program manager of the OFE Program. You are working with your program team and project managers to ensure that there is consistency in the execution of the program plan. You stress that the work has been planned and now the team must accurately complete the work. You want to ensure that the work is done correctly the first time in the program. What type of process are you stressing to your program team and project managers?

A.
Quality assurance
A.
Quality assurance
Answers
B.
Scope verification
B.
Scope verification
Answers
C.
Quality control
C.
Quality control
Answers
D.
Process improvement
D.
Process improvement
Answers
Suggested answer: A

You are the program manager for your company and are monitoring and controlling several aspects of your program. You want to make certain that you're including all areas that need to be monitored and controlled. Which one of the following is not something you'll have to monitor and control as a program manager?

A.
Materials required by the program
A.
Materials required by the program
Answers
B.
Equipment your program uses
B.
Equipment your program uses
Answers
C.
Susan the application developer in your program
C.
Susan the application developer in your program
Answers
D.
Stakeholder identification
D.
Stakeholder identification
Answers
Suggested answer: D

A program has a budget at completion of $1,250,000 and has already spent $425,000. The program is running late due to some vendor delays; the program is only 30 percent complete though it was scheduled to be 45 percent at this time. Based on this information how much more money will this program need to finish?

A.
$978,445
A.
$978,445
Answers
B.
$919,325
B.
$919,325
Answers
C.
$991,667
C.
$991,667
Answers
D.
$987,544
D.
$987,544
Answers
Suggested answer: C

Your program has a budget at completion of $1,550,000 and is expected to last one year.

Currently your program is 45 percent complete and has spent $725,000. According to the program schedule you are actually to be fifty percent complete by this time, but due to some vendor delays your program is running just a bit late. Based on this information which is performing worse, the cost or schedule?

A.
The schedule is performing worse because the SPI is .90
A.
The schedule is performing worse because the SPI is .90
Answers
B.
The cost is performing worse because the EAC is $1,611,111.
B.
The cost is performing worse because the EAC is $1,611,111.
Answers
C.
The schedule is performing worse because the SV is -$27,500.
C.
The schedule is performing worse because the SV is -$27,500.
Answers
D.
The cost is performing worse because the CPI is .96.
D.
The cost is performing worse because the CPI is .96.
Answers
Suggested answer: A

Which of the following is not a template element that is designed to make the project more effective?

A.
Description of the work packages
A.
Description of the work packages
Answers
B.
Required resources and skills
B.
Required resources and skills
Answers
C.
Required actions to complete the project scope
C.
Required actions to complete the project scope
Answers
D.
Contract file
D.
Contract file
Answers
Suggested answer: D

You are coaching Tammy, a project manager in your program, on the benefits of program management. She is stumped as to why you would create a program so you're sharing with her all the difference benefits of a program. Which one of the following is a benefit of creating a program?

A.
Programs always cost less than multiple projects in an organization.
A.
Programs always cost less than multiple projects in an organization.
Answers
B.
Project management is centralized to the program manager.
B.
Project management is centralized to the program manager.
Answers
C.
Programs provide centralized risk management.
C.
Programs provide centralized risk management.
Answers
D.
Program management makes communication easier among the project managers and project team.
D.
Program management makes communication easier among the project managers and project team.
Answers
Suggested answer: C

Part of program management is to identify what motivates your program team members. If you subscribe to Maslow's Hierarchy of Needs, which need is at the top of the hierarchy?

A.
Physiological
A.
Physiological
Answers
B.
Safety
B.
Safety
Answers
C.
Self actualization
C.
Self actualization
Answers
D.
Esteem
D.
Esteem
Answers
Suggested answer: C

Your program exists within a matrix structure. Your program has eight projects that all share resources from around the organization. You are concerned that some of the project team members may be over allocated and want to create a chart that will reflect the utilization of resources. What kind of chart can show the utilization of project team members used in your program?

A.
Resource network diagram
A.
Resource network diagram
Answers
B.
Resource breakdown structure
B.
Resource breakdown structure
Answers
C.
Resource histogram
C.
Resource histogram
Answers
D.
Pareto chart
D.
Pareto chart
Answers
Suggested answer: C