ExamGecko
Home / PMI / PgMP / List of questions
Ask Question

PMI PgMP Practice Test - Questions Answers, Page 5

Add to Whishlist

List of questions

Question 41

Report Export Collapse

You are the program manager for your organization. You are examining the order of the activities in your program schedule and would like to change some of the ordering to alleviate scheduling conflicts, risks, and based on your experience with the discipline the program uses. Some of the activities you can rearrange while some of the activities must be completed in a particular order. What term describes the activities that can happen in any order?

Finish on constraints
Finish on constraints
Discretionary dependencies
Discretionary dependencies
Mandatory dependencies
Mandatory dependencies
Benefits management dependencies
Benefits management dependencies
Suggested answer: C
asked 23/09/2024
Vasco Rodrigues
43 questions

Question 42

Report Export Collapse

You are the program manager for your organization and are planning the roles and responsibilities in your program. You would like to create a RACI chart for the program work. What does RACI mean?

It is a roles and responsibilities chart that uses responsible, accountable, consult, and inform responsibilities as the chart legend.
It is a roles and responsibilities chart that uses responsible, accountable, consult, and inform responsibilities as the chart legend.
It is a roles and responsibilities chart that uses responsible, action, consult, and interest responsibilities as the chart legend.
It is a roles and responsibilities chart that uses responsible, action, consult, and interest responsibilities as the chart legend.
It is a roles and responsibilities chart that uses resource, action, contribute, inform responsibilities as the chart legend.
It is a roles and responsibilities chart that uses resource, action, contribute, inform responsibilities as the chart legend.
It is a roles and responsibilities chart that uses responsible, accountable, contribute, and inform responsibilities as the chart legend.
It is a roles and responsibilities chart that uses responsible, accountable, contribute, and inform responsibilities as the chart legend.
Suggested answer: A
asked 23/09/2024
PrzemysΓ…‚aw Doczkal
50 questions

Question 43

Report Export Collapse

You are the program manager of the OFE Program. You are working with your program team and project managers to ensure that there is consistency in the execution of the program plan. You stress that the work has been planned and now the team must accurately complete the work. You want to ensure that the work is done correctly the first time in the program. What type of process are you stressing to your program team and project managers?

Quality assurance
Quality assurance
Scope verification
Scope verification
Quality control
Quality control
Process improvement
Process improvement
Suggested answer: A
asked 23/09/2024
Novka Mandic
40 questions

Question 44

Report Export Collapse

You are the program manager for your company and are monitoring and controlling several aspects of your program. You want to make certain that you're including all areas that need to be monitored and controlled. Which one of the following is not something you'll have to monitor and control as a program manager?

Materials required by the program
Materials required by the program
Equipment your program uses
Equipment your program uses
Susan the application developer in your program
Susan the application developer in your program
Stakeholder identification
Stakeholder identification
Suggested answer: D
asked 23/09/2024
Lakshmi Yechuri
45 questions

Question 45

Report Export Collapse

A program has a budget at completion of $1,250,000 and has already spent $425,000. The program is running late due to some vendor delays; the program is only 30 percent complete though it was scheduled to be 45 percent at this time. Based on this information how much more money will this program need to finish?

$978,445
$978,445
$919,325
$919,325
$991,667
$991,667
$987,544
$987,544
Suggested answer: C
asked 23/09/2024
Barbara Bailey
45 questions

Question 46

Report Export Collapse

Your program has a budget at completion of $1,550,000 and is expected to last one year.

Currently your program is 45 percent complete and has spent $725,000. According to the program schedule you are actually to be fifty percent complete by this time, but due to some vendor delays your program is running just a bit late. Based on this information which is performing worse, the cost or schedule?

The schedule is performing worse because the SPI is .90
The schedule is performing worse because the SPI is .90
The cost is performing worse because the EAC is $1,611,111.
The cost is performing worse because the EAC is $1,611,111.
The schedule is performing worse because the SV is -$27,500.
The schedule is performing worse because the SV is -$27,500.
The cost is performing worse because the CPI is .96.
The cost is performing worse because the CPI is .96.
Suggested answer: A
asked 23/09/2024
Cristian Pernia
46 questions

Question 47

Report Export Collapse

Which of the following is not a template element that is designed to make the project more effective?

Description of the work packages
Description of the work packages
Required resources and skills
Required resources and skills
Required actions to complete the project scope
Required actions to complete the project scope
Contract file
Contract file
Suggested answer: D
asked 23/09/2024
josh hill
41 questions

Question 48

Report Export Collapse

You are coaching Tammy, a project manager in your program, on the benefits of program management. She is stumped as to why you would create a program so you're sharing with her all the difference benefits of a program. Which one of the following is a benefit of creating a program?

Programs always cost less than multiple projects in an organization.
Programs always cost less than multiple projects in an organization.
Project management is centralized to the program manager.
Project management is centralized to the program manager.
Programs provide centralized risk management.
Programs provide centralized risk management.
Program management makes communication easier among the project managers and project team.
Program management makes communication easier among the project managers and project team.
Suggested answer: C
asked 23/09/2024
Aubrey Oliver Jr
43 questions

Question 49

Report Export Collapse

Part of program management is to identify what motivates your program team members. If you subscribe to Maslow's Hierarchy of Needs, which need is at the top of the hierarchy?

Physiological
Physiological
Safety
Safety
Self actualization
Self actualization
Esteem
Esteem
Suggested answer: C
asked 23/09/2024
David Hartnett
46 questions

Question 50

Report Export Collapse

Your program exists within a matrix structure. Your program has eight projects that all share resources from around the organization. You are concerned that some of the project team members may be over allocated and want to create a chart that will reflect the utilization of resources. What kind of chart can show the utilization of project team members used in your program?

Resource network diagram
Resource network diagram
Resource breakdown structure
Resource breakdown structure
Resource histogram
Resource histogram
Pareto chart
Pareto chart
Suggested answer: C
asked 23/09/2024
Pachara Suwannasit
37 questions
Total 451 questions
Go to page: of 46
Search

Related questions