A program manager initiates a developmental program. Significant resources and funding are required for early activities until the program cost and budget estimates are complete.

What should the program manager do to understand the financial environment?

A.
Map costs to the expected benefits realization.
Answers
A.
Map costs to the expected benefits realization.
B.
Establish intermediate budget based on historical information.
Answers
B.
Establish intermediate budget based on historical information.
C.
Establish program financial framework.
Answers
C.
Establish program financial framework.
D.
Obtain intermediate funding from the executive sponsor.
Answers
D.
Obtain intermediate funding from the executive sponsor.
Suggested answer: B