Question 395 - PgMP discussion
The program charter for a new, five-component program has been approved.
What should the program manager use to communicate the program's intended direction and the linkage between organizational strategies and planned work?
A.
Program roadmap
B.
Program charter
C.
Program business case
D.
Program management plan
Your answer: