Andy is the program manager of the HQN Program. This program is nearing its completion and there is still $25,000 left in the program budget. Andy has asked the program team to identify some extra deliverables that can be included in the program scope to improve the program deliverable but also to use all of the funds in the budget. What term is assigned to the actions that Andy is trying to do in this instance?

A.
Value-added change requests
Answers
A.
Value-added change requests
B.
Zero based budgeting
Answers
B.
Zero based budgeting
C.
Integrated change control
Answers
C.
Integrated change control
D.
Gold plating
Answers
D.
Gold plating
Suggested answer: D