Question 393 - PgMP discussion
Throughout a multiyear program, component projects are transitioned to the customer. During the project acceptance phase, a potential risk is identified and brought to the program team's attention.
What should be done with the identified potential risk?
A.
Incorporate it into the risk register and perform a thorough analysis.
B.
Mitigate the risk before it is incorporated into the risk management plan.
C.
Document the risk in the program transition plan and identify it as a potential issue.
D.
Document it in the issue log and immediately notify the steering committee.