A program manager needs to establish direction and identify the essential aspects of a program. In addition, they must ensure that the context and framework of the program are properly defined, assessed, and documented.

Which document will be created to support this activity?

A.
Program resource management plan
Answers
A.
Program resource management plan
B.
Program management plan
Answers
B.
Program management plan
C.
Program master schedule
Answers
C.
Program master schedule
D.
Program scope statement
Answers
D.
Program scope statement
Suggested answer: D