You are the program manager for your organization. You and your program team have been creating and transferring the program benefits to operations as feasible in your program execution. The process of delivering the program's benefits describes what process in program management?

A.
Quality control
Answers
A.
Quality control
B.
Benefits management
Answers
B.
Benefits management
C.
Direct and manage program execution
Answers
C.
Direct and manage program execution
D.
Quality assurance
Answers
D.
Quality assurance
Suggested answer: C